This expansion wasn't done lightly. FIDIC added provisions to address key contracting concerns that were omitted from the 1999 version. Here are the most important changes:
To avoid the frequent disputes surrounding delay compensation found in the 1999 edition, the 2021 version introduces a sophisticated formulaic approach to Contractor’s Prolongation Costs (CPC). If the contractor is delayed by an Employer-risk event, compensation is calculated using a pre-agreed formula defined in the Contract Data, reducing subjective negotiation and administrative gridlock. 3. Clearer Risk Allocation
The 2021 contract introduces a clearer distinction between claims (managed by the Engineer) and disputes (referred to an Adjudicator). It includes two distinct contractual routes to handle claims and variations, along with new grounds for termination, such as failing to comply with an Engineer's or Adjudicator's determination.
: It accommodates multiple payment options, including Lump Sum, Re-measurement, Cost Reimbursable, or bespoke combinations. 2. Structural Overhaul and Document Priority
Shorter, simpler language reduces procurement timelines and contract negotiation costs. short form of contract 2nd ed -2021 green book- pdf
The is specifically designed as a "Short Form of Contract." The original 1st Edition was released in 1999. After more than two decades of industry evolution, FIDIC released the 2nd Edition in December 2021 to address modern project complexities while retaining the book's signature brevity and ease of use. Key Updates in the 2nd Edition (2021)
Projects where the perceived level of technical and commercial risk is low.
This public link is valid for 7 days and shares a thread, including any personal information you added. This link or copies made by others cannot be deleted. If you share with third parties, their policies apply. Can’t copy the link right now. Try again later.
This comprehensive guide will walk you through everything you need to know about the FIDIC Short Form of Contract, Second Edition (2021) — widely known as the "Green Book." We'll explore its purpose, key features, what's changed from the 1999 edition, how it compares to FIDIC's other famous contracts (the Red and Yellow Books), and provide authoritative information on how to purchase a legitimate PDF copy. This expansion wasn't done lightly
The 2021 Second Edition represents a significant evolution from the 1999 version. It introduces greater clarity, enhanced project management mechanisms, and formalized dispute resolution procedures, expanding from 15 to 26 pages of general conditions. 1. Introduction of the "Engineer"
The FIDIC Green Book is generally recommended for projects that meet the following criteria:
By using the correct 2021 Green Book, you save money on legal fees, speed up project delivery, and protect both the employer and the contractor from catastrophic disputes.
is a streamlined alternative to the more complex Red and Yellow Books, designed for projects where the . While the 1999 edition was strictly for small-value works, the 2021 version is flexible enough for projects exceeding $10 million in capital value. 📥 Accessing the Document If the contractor is delayed by an Employer-risk
| Clause Section | Information Required | Common Mistake | | :--- | :--- | :--- | | | Names and addresses of Employer & Contractor | Using nicknames instead of legal entity names. | | Clause 2.1 | The Scope/Works Information | Just writing "see drawings" without attaching the drawings. | | Clause 3.1 | Commencement Date & Completion Date | Failing to specify "Time is of the Essence." | | Clause 6.1 | The Contract Sum (Price) | Forgetting to state if it's fixed or adjustable for inflation. | | Clause 8.1 | Defects Liability Period | Usually 12 months, but can be changed. | | Clause 9.1 (Option Z) | Additional conditions of contract | This is a blank slate. Add your site-specific rules here. |
For your next small to medium-sized project, the FIDIC Green Book 2nd Edition is an excellent choice. Just remember to purchase your official copy from an authorized source and to seek proper legal advice before use.
The 2021 edition contains approximately 30 clauses, compared to over 100 in standard long-form contracts. It covers: